Green Garden Infiltration Wells Construction Estimated to Finish Within a Week

In a week, modular tank infiltration wells construction carried out on Jl. Kompleks Green Garden Blok L, RT 12/04, Kedoya Utara, Kebon Jeruk, West Jakarta will be completed.

Since this is the final touch, we estimate it to finish within a week

Kebon Jeruk Sub-district Water Resources (SDA) Unit Head, Suprapto stated, infiltration well construction whad been started since November 14. Infiltration wells were built along 100 meters with capacity of 300 cubic meters.

"Since this is the final touch, we estimate it to finish within a week," he said, Thursday (12/17).

92 Infiltration Wells Built in West Jakarta

His side deployed 7 SDA Unit personnel to build it. Infiltration well has size of 4 meters long, 3 meters wide, and 1.5 meters deep. Each of them installed with 54 modular tanks.

"The advantages of infiltration wells with modular tanks are lighter, faster to build, don't need heavy equipment, have stronger structure and don't need maintenance," he conveyed.

Linked News
Popular News indeks
  1. New LapakMain Corner Creative Hub Inaugurated at Tunas Muda RPTRA, Kramat Pela

    access_time05-08-2026 remove_red_eye563 personTiyo Surya Sakti
  2. Still Rp 3,500! No Fare Change for Transjakarta’s Kalideres–Soetta Route

    access_time01-08-2026 remove_red_eye562 personAldi Geri Lumban Tobing
  3. Jakarta Claims Rp 2.27 T in Public Assets from Developer Obligations

    access_time06-08-2026 remove_red_eye426 personDessy Suciati
  4. Jakarta Gov Revs Up Efforts to Become Indonesia's Sport Tourism Hub

    access_time01-08-2026 remove_red_eye411 personFolmer
  5. Betawi Heritage Takes Center Stage at the 4th Betawi Mask Festival

    access_time01-08-2026 remove_red_eye406 personNurito